skip to Main Content

Berean Parking Lot

Project Overview

CWI was contracted to construct a new parking lot, driveways, and storm systems. The project consisted of clearing and grubbing of the disturbed area, including blasting and removing over 6,000 cubic yards of rock. The construction of the new parking lot, landscape areas, and the necessary stormwater management facilities, and the erosion control practices and techniques were to comply with the NPDES GAR100001 requirements.

Project Details

  • Project Type: Parking Lot Expansion
  • Proposed Date of Completion: August 2020
  • Actual Dat of Completion: August 2020
  • Firm’s Responsibility: Ugrades
  • Size: 4.42 acres
  • Original: $1.45M
  • Final:$1.79M